Primary School refurbishment update

This week's newsletter for Cromarty Primary School parents and pupils reports that the contract for refurbishment (phase one) has been awarded to Morgan Sindall. The contractor will move on-site in December ready to begin work on the extension phase in January 2015. Phase two (renovation of old part of building) is expected to commence during the summer 2015 school holiday with completion estimated for November 2015.